Overall Equipment Effectiveness (OEE) answers one blunt question: of the time a machine was supposed to be making good parts, how much of it actually did? It's one of the most useful numbers in manufacturing, and one of the most often wrong, because it's still calculated from handwritten logs filled in at the end of a shift.

This guide shows how OEE is calculated, why manual OEE usually looks better than reality, and what you need to measure it automatically.

The OEE formula

OEE multiplies three factors:

OEE = Availability × Performance × Quality

FactorQuestion it answersFormulaLosses it captures
AvailabilityWas the machine running when it was planned to?Run time ÷ Planned production timeBreakdowns, changeovers, waiting for material or operators
PerformanceWhen running, was it running at full speed?(Ideal cycle time × Total count) ÷ Run timeSlow cycles, small stops
QualityWere the parts good?Good count ÷ Total countScrap, rework, start-up rejects

A worked example

One machine, one 8-hour shift:

ItemValue
Shift length480 minutes
Planned breaks30 minutes
Planned production time450 minutes
Stoppages (breakdown + changeover)45 minutes
Run time405 minutes
Ideal cycle time30 seconds per part (0.5 minutes)
Total parts made700
Good parts680
  • Availability = 405 ÷ 450 = 90.0%
  • Performance = (0.5 × 700) ÷ 405 = 350 ÷ 405 = 86.4%
  • Quality = 680 ÷ 700 = 97.1%
  • OEE = 0.900 × 0.864 × 0.971 = 75.6%

Quick check: good parts × ideal cycle time ÷ planned time = (680 × 0.5) ÷ 450 = 75.6%. Same answer.

These figures are an example, not a benchmark.

What "good" OEE looks like

The figure most often quoted as "world class" is 85%: roughly 90% availability, 95% performance and 99.9% quality. It's credited to Seiichi Nakajima, who developed Total Productive Maintenance (TPM) in Japan.

Treat 85% as a direction, not a pass mark. It came from high-volume automotive lines, and benchmark studies suggest only a small share of plants reach it. What matters most is your own trend, measured the same way every week.

Why manual OEE is usually wrong

When OEE comes from shift logs, three things happen:

  1. Small stops disappear. A 2-minute jam isn't written down. Twenty of them a shift is 40 minutes, about 9% of the planned time in our example, and it vanishes from the log.
  2. Times are rounded. "Stopped 10:00 to 10:30" is rarely exactly right, and rounding tends to flatter the result.
  3. Reasons are vague. "Machine problem" doesn't tell maintenance anything. Without specific reasons you can't fix the biggest loss.

The result: manual OEE often looks better than reality, and the losses that matter most (small stops and slow cycles) are the ones it misses.

The six big losses

TPM groups production losses into six categories. Automatic OEE should tell you which one is costing you most.

LossOEE factorTypical source of the signal
BreakdownsAvailabilityMachine stopped + reason
Setup and adjustments (changeovers)AvailabilityMachine stopped + "changeover" reason
Small stops (jams, sensor trips, under ~5 minutes)PerformanceShort gaps in the run signal or part count
Reduced speedPerformanceCycle time slower than ideal
Start-up rejectsQualityRejects counted after a changeover
Production rejectsQualityRejects during steady running

What you need to measure OEE automatically

SignalWhere it comes from
Run state (running, idle, stopped)A PLC "run" bit, or a current clamp on the main motor
Part countA PLC counter, or a proximity or photo sensor at the output
Reject countA PLC counter, a reject chute sensor, or operator input
Planned production timeShift calendar and planned breaks, entered once
Ideal cycle timePer product, from engineering. This is the number most plants have to agree on first
Stop reasonsOperator selects a reason on a tablet or button box when a stop exceeds a set time. PLC alarm codes where available

Many of these signals are already inside your PLCs and can be read without changing the machine's program. For machines without a controller, add-on sensors fill the gaps. (See retrofitting old machines and PLCs for IoT.)

From OEE number to action

An OEE dashboard is only useful if it changes what happens on the floor:

  • Shift start: yesterday's OEE by machine, and the top three loss reasons.
  • During the shift: an alert when availability on a machine drops below a threshold for more than a set time. For example, our platform can raise an alert like "Line 2 CNC-3 availability 54% for 15 minutes" and turn it into a work order in the ERP automatically.
  • Weekly: losses ranked by minutes lost (a Pareto chart). Fix the biggest one first.

OEE software: build, buy or both?

OptionGood whenWatch out for
Spreadsheet from manual logsGetting started, 1–2 machinesMisses small stops and slow cycles
Off-the-shelf OEE softwareStandard machines and processesConnecting your mix of old and new machines may cost more than the licence
Custom or configurable platform + IoTA mixed machine park, integration with ERP or MES, other monitoring (energy, condition) on the same systemNeeds a clear scope and a pilot

OEE is one part of real-time machine monitoring. Our Factory OS platform tracks OEE alongside predictive maintenance on the same system.

Frequently asked questions

How do you calculate OEE?

Multiply availability (run time ÷ planned time), performance (ideal cycle time × total count ÷ run time) and quality (good count ÷ total count). See the worked example above.

Is 85% OEE realistic?

It's an often-quoted "world class" figure, not a typical one. Many plants run well below it. Focus on improving your own measured trend.

Can we measure OEE on old machines?

Yes. A current clamp gives run state and an output sensor gives part count, even on machines with no PLC. Add a simple way for operators to record stop reasons.

What's the difference between OEE and machine utilisation?

Utilisation usually compares run time with total calendar time. OEE compares good output with what was possible in the planned time, so it also captures speed and quality losses.

How long before automatic OEE shows results?

The first honest baseline usually appears within a few weeks of reliable data. Improvement depends on acting on the top loss reasons each week.

Want to see OEE measured live? Our factory demo includes an OEE and bottleneck scenario running on the same platform we deploy. Run the factory demo → · Talk to us about an OEE pilot →

Let's Work Together

Contact Us and We'll Help You

Whether you have a question, an idea, or a project in mind, our team is ready to assist you every step of the way.