The hard part of industrial IoT isn't getting a dashboard to light up. It's getting from "the pilot worked" to "finance approved the rollout". This problem has a name, pilot purgatory, and it's old. In McKinsey's 2018 survey of 700 manufacturers, about 70% had started piloting Industry 4.0 solutions, but only 29% were capturing value from them at scale.
Pilots usually don't fail on technology. They fail because nobody agreed in advance what success looked like, there was no "before" number to compare against, or the rollout had no owner and no budget.
This is a 90-day plan built to avoid those traps. It works for machine monitoring, energy monitoring, cold-chain monitoring and most other "connect assets and act on the data" projects.
What a pilot has to prove
A pilot must answer three questions. If it only answers the first one, you'll be asked to "run it a bit longer".
| Question | Who asks it | What proves it |
|---|---|---|
| Does it work here? | Engineering, IT | Reliable data from your machines, in your conditions, for weeks |
| Will people use it? | Operations, maintenance | Alerts that someone acts on, and a dashboard used in real meetings |
| Is it worth the money? | Finance, management | A measured improvement against a baseline, and a costed rollout plan |
Before day 1: four decisions
1. Pick one problem, not a platform. "Reduce unplanned stoppages on Line 2" is a pilot. "Digitise the plant" is not. Choose a problem that costs real money, happens often enough to measure in 90 days, and involves 3–10 assets.
2. Agree the baseline. Write down today's number before anything is installed: stoppage hours per week, energy units per tonne, temperature excursions per month. If there's no reliable record, the first two weeks of the pilot become the baseline period.
3. Write the success criteria, and get them signed. Both sides sign a one-page document. For example:
| Type | Example criterion |
|---|---|
| Data | At least 98% of expected readings received over the last 4 weeks |
| Use | Every critical alert acknowledged within 30 minutes during shift hours |
| Value | Stoppage hours on the pilot machines down against the baseline, with each avoided stoppage logged |
| Rollout | A per-asset cost and install time that fits the budget for the full line |
The figures above are examples to adapt, not industry benchmarks.
4. Name two owners. A business owner who will present the result to management, and an IT/OT owner who controls network access, security approval and integration. McKinsey calls the gap between IT and operations "the last IT/OT mile". It's where many pilots quietly die.
The 90-day plan
| Phase | Weeks | What happens | You get |
|---|---|---|---|
| 1. Survey and baseline | 1–2 | Site visit, machine-by-machine survey (controllers, meters, power, network, mounting points), security review, baseline data collection starts | Survey report, final asset list, signed success criteria |
| 2. Install and connect | 3–6 | Sensors and gateways installed, PLCs and meters connected, data flowing to the platform, first dashboards | Live data from every pilot asset, data-quality report |
| 3. Run and tune | 7–10 | Alert thresholds tuned with the maintenance team, weekly review meetings, first actions taken on alerts, integration with the maintenance or ERP system if in scope | Alert log with actions, weekly reports |
| 4. Measure and decide | 11–13 | Compare against the baseline, calculate value, cost the rollout, present to management | Pilot report and rollout proposal |
Phase 1: survey and baseline (weeks 1–2)
The survey decides the cost of everything that follows. For each asset, record:
- Make, model and year, and whether it has a PLC or controller (and which one).
- Whether that controller or the energy meter can be read over Modbus, OPC UA or another protocol.
- Where a sensor can be mounted safely, and where power is available.
- Network reach: Wi-Fi signal, mobile signal, or whether a cable or LoRa link is needed.
- Who must approve panel access and any electrical work.
(Our guide to retrofitting old machines and PLCs covers the survey in detail.)
Phase 2: install and connect (weeks 3–6)
Start with data quality, not dashboards. Check every signal against a physical reading: a handheld meter, the machine's own display, a manual count. A dashboard full of wrong numbers loses the operators' trust in the first week, and you won't get it back.
Rule of thumb: a missing reading is better than a wrong one. The system should flag gaps clearly rather than fill them with guesses.
Phase 3: run and tune (weeks 7–10)
Early alert thresholds are always wrong. Too sensitive, and people learn to ignore them. Too relaxed, and you miss the event. Hold a 30-minute review every week with the maintenance lead to adjust thresholds and to record what action each alert led to. That action log becomes your proof of value.
If the pilot includes integration, this is when alerts start creating work orders in your maintenance or ERP system automatically. (See how an IoT alert becomes an ERP work order.)
Phase 4: measure and decide (weeks 11–13)
The pilot report should fit on four pages:
- Result against each success criterion: met, partly met or not met, with the numbers.
- Value: what improved against the baseline, and what that's worth per year at full scale. Be conservative and show your workings. (Our IoT ROI guide shows how.)
- Rollout plan: number of assets, cost per asset (hardware, installation, connectivity, software), monthly running cost, timeline, and who supports it.
- Risks and open questions: what you'd do differently at scale.
Why pilots stall, and how to prevent it
| Cause | Prevention |
|---|---|
| No baseline, so no proof | Measure "before" in weeks 1–2, even manually |
| Too many use cases at once | One problem, 3–10 assets |
| IT security approval arrives in month 3 | Involve IT/OT in week 1. Share the device security design up front |
| Alerts nobody acts on | Weekly tuning with maintenance. Log the action for every alert |
| The pilot "works" but nobody costs the rollout | The rollout plan is a deliverable, not an afterthought |
| The champion changes jobs | Two named owners, and a management review date agreed on day 1 |
Frequently asked questions
How much does an industrial IoT pilot cost?
It depends mainly on the number of assets, whether they can be read through existing controllers or need new sensors, network work, and whether integration is in scope. Ask vendors for a fixed-price pilot with the cost split into hardware, installation, software and engineering, so you can compare like for like.
How many machines should a pilot include?
Usually 3–10. Fewer, and you can't tell a pattern from a coincidence. More, and the pilot becomes a small rollout.
Can we pilot with sensors and meters we already have?
Often, yes. Many energy meters, PLCs and drives already expose their readings over Modbus. That cuts hardware cost and installation time.
Who should own the data from the pilot?
You should. Put it in the contract: your data, exportable in an open format, whether or not you continue with the vendor.
What if the pilot misses its targets?
That's still a useful result if you learn why. Was the data reliable? Were alerts acted on? Was the problem smaller than thought? A good pilot report says so plainly.